CHAPTER 13
MINISTRY OF HEAVY INDUSTRIES AND PUBLIC ENTERPRISES
Bharat Heavy Electricals Limited
13.1.1 Loss due to design deficiency in supply of coal
handling plants
The Company incurred avoidable expenditure of Rs. 4 crore due
to rectification of coal handling plants purchased from a supplier, which went
into liquidation.
Hyderabad Unit of Bharat Heavy Electricals Limited (Company)
floated limited tender enquiries for design and supply of coal handling plants (CHPs).
These were required for execution of two orders from Coal India Limited,
Calcutta for establishing 2x10MW Fluidised Bed Combustion (FBC) Boiler-based
captive thermal power stations at Moonidih and Kathara in Bihar. The supplier,
Bulk Systems International Limited (BSIL), Bangalore was selected (July 1989) at
a contract price of Rs. 6.53 crore and delivery was scheduled for November 1990.
The supplier went into liquidation before completing supplies
of CHPs. The Company, however, ensured the completion of supplies to its
customer by dealing directly with BSIL’s sub-vendors. When the thermal power
stations at both the sites were synchronised in June 1993/February 1994, the
screening facility of CHPs was found to be defective. Although the tender
specifications stipulated screening of crushed coal, the CHPs at both the sites
failed to give the desired level of coal output due to design deficiency in the
screening system.
To overcome the deficiency the Company modified the CHPs and
also installed (December 1995/ November 1996) additional screening facilities at
both the sites. The TG sets were finally commissioned in March 1996 (Kathara) /
March 1997 (Moonidih).
There was, thus a delay of 6 years in installing the CHPs
from the date originally envisaged for commissioning. In the process, the
Company incurred total additional expenditure amounting to Rs. 4 crore (cost of
modification of CHPs plus installation of additional screening facilities).
In response, the Ministry stated (April 2001) that the
deficiency in the design of CHP came to light only during the commissioning of
the plant. The impact crushers failed due to the presence of a large percentage
of shale in the raw coal and that the Company had not foreseen the supply of
this type of coal by the customer at the design stage. It also stated that the
Company had to absorb the additional cost of Rs.4 crore as modification of coal
handling facilities while its price escalation claims to the tune of Rs.10.50
crore though agreed to in October 1994 had not been released so far. Further,
although execution of this order culminated in cost overrun, these costs could,
however, be absorbed as Hyderabad Unit has been making profit during all the
years.
The reply of the Ministry is not tenable as the Company was
forced to absorb the additional cost of Rs.4 crore towards modifications in CHPs,
as it had selected a contractor without ensuring his technical and financial
soundness. This also multiplied the overall delays in execution of the project.
Moreover, the fact that Hyderabad Unit had been continuously making profits can
not absolve the Company of uneconomical execution of a contract.
Thus, due to the avoidable delays in supplies and in
rectification of CHPs, the Company incurred an extra expenditure of Rs.4 crore.
13.1.2 Blocking of funds with consequential loss of interest
Due to acceptance of terms of payment for sending despatch
documents directly to the firms instead of routing through the bank, there was
delay in realisation of value of equipment supplied by the Company. This
resulted into loss of interest of Rs.2.12 crore, besides undue financial benefit
to the private parties.
The general terms and conditions followed by M/s. Bharat
Heavy Electricals Limited (Company) for sale of equipment provided for 10 per
cent payment as advance along with the order, 30 per cent on completion of 50
per cent of the delivery and balance 60 per cent along with price variations and
taxes and duties against despatch documents through the bank. In two cases the
Company not only deviated from the standard conditions but also failed to
enforce the conditions agreed to, resulting in blocking up of funds to the tune
of Rs. 5.35 crore and loss of interest of Rs.2.12 crore as discussed below.
Case (A)
The Company received (January 1997) an order from M/s. Jindal
Vijayanagar Steel Limited (JVSL) for supply of four numbers of 700 HP diesel
electric shunting locomotives at a total price of Rs.5.36 crore excluding taxes
and duties. The payment terms accepted by the Company in the order provided for
10 per cent payment as advance, 80 per cent on presentation of invoice after
receipt of the locomotives at site and 10 per cent after commissioning.
After despatching two locomotives in March 1997, the Company
raised invoices for Rs. 2.67 crore. Despite the fact that payment was not
received for the despatches made in March 1997, the Company further despatched
remaining two locomotives in March 1998 and raised another invoice for Rs.2.67
crore. Besides, the Company also raised invoices for an amount of Rs.58.85 lakh
towards commissioning and service charges during the period February 1998 to
September 1998.
As per the terms of the order, JVSL was required to make
payment in March 1997 and March 1998. However, JVSL paid an amount of Rs.5.31
crore in instalments from May 1998 to March 2001, with a balance of Rs.61.99
lakh still outstanding (March 2001).
This resulted in blocking of the Company's funds for more
than four years along with consequential loss of interest of Rs. 1.27 crore,
besides undue financial benefit to the party.
Case (B)
The Company accepted (September 1998) a letter of Award (LOA)
from M/s. Neelachal Ispat Nigam Limited (NINL) for supply and commissioning of
four Diesel Electric Locomotives at a price of Rs. 5.90 crore inclusive of taxes
and duties.
Though the Company despatched all the locomotives in March
2000 and raised invoices amounting to Rs. 4.73 crore, the party failed to make
the payments in accordance with the terms of the order. Despite being reminded
by the Company, the party was yet to release the amount (August 2001). Further,
an amount of Rs. 73.50 lakh was yet to be billed due to non-receipt of
preliminary acceptance certificate from the party. (August 2001).
This resulted in blocking of the Company's funds to the
extent of Rs. 5.47 crore and consequential loss of interest of Rs. 84.83 lakh.
The Management stated (September 2001) that the deviation
from the general terms of sales of equipment was necessitated by purely
commercial considerations and changes in the payment terms were agreed upon so
as not to lose the order.
The reply is not tenable, as the Company should have
safeguarded its financial interests while accepting the deviation in the
standard terms of payment. Also, the Company could not enforce the payment terms
of the order due to accepting to send despatch documents directly to the party
instead of routing through bank. This was not a prudent financial decision,
which amounted to extending undue benefit to the customers while resulting in
loss of interest amounting to Rs. 2.12 crore to the Company. Further, an amount
of Rs.5.35 crore was yet to be realised as of August 2001.
The matters were referred to the Ministry in June/July 2001;
their replies were awaited (October 2001).
13.1.3 Blocking of funds and consequential loss of interest
The Company manufactured and supplied nine motors without
obtaining the requisite clearance of Northern Coalfields Limited (NCL) regarding
satisfactory performance of motors supplied earlier as required by the terms and
conditions of the supply order. Due to frequent failure of the earlier motors,
NCL withheld the balance payment. This resulted in blocking of the Company's
funds amounting to Rs. 1.52 crore for more than six years, besides entailing
avoidable loss of interest of Rs. 1.50 crore.
Bharat Heavy Electricals Limited (Company) received a supply
order from Northern Coalfields Limited (NCL) in November 1991 for supply of nine
Float Motors (motors) at a total cost of Rs. 1.91 crore. As per the supply
order, delivery of motors was to commence within 11 months and completed within
16 months from the date of receipt of the order, subject to the condition that
eight motors out of the total nine were to be supplied only after getting
clearance from NCL regarding satisfactory performance of similar motors supplied
earlier by the Company. In fact, the Company had supplied similar motors for
replacing the imported ones during the period from February 1992 to September
1993.
Despite the above terms and conditions, the Company
manufactured and supplied all the nine motors during the period July 1992 to
July 1994 without taking clearance regarding satisfactory performance of earlier
motors.
After releasing a sum of Rs. 59.79 lakh (upto April 1994),
NCL withheld the balance payment of Rs. 1.52 crore including escalation of Rs.
21 lakh, pending clearance of satisfactory performance of the earlier motors.
NCL stated that as the earlier motors supplied by the Company had failed
frequently, the balance payment would be released only after satisfactory
performance of all the motors.
The Company, however, could not enforce the release of
balance payment, as it did not seek the clearance from NCL either before
commencing the process of manufacturing or before starting the delivery of
motors. Moreover, the supply order did not contain any time limit within which
NCL was required to give the requisite clearance.
The Management stated (July 2000) that release of 25 per cent
of the payment due implied clearance of despatch of the motors. Further,
non-release of the balance amount was due to the inability of NCL to put motors
on trial and not due to non-adherence to the terms of the supply order.
The reply of the Management is not tenable because the
Company would have avoided the blocking of its funds, had it adhered to the
terms of the supply order by obtaining the requisite clearance especially in
view of the special nature of the motors. Further, 25 per cent of the payment
was released by NCL only on ad hoc basis, with a clear indication that
the balance payment would be released only after satisfactory performance of the
motors.
Thus, the Company’s failure in not obtaining the requisite
clearance before commencing the manufacturing resulted in blocking of funds to
an extent of Rs. 1.52 crore for more than six years with consequential loss of
interest amounting to Rs. 1.50 crore.
The matter was referred to Ministry in April 2001; their
reply was awaited (October 2001).
13.1.4 Avoidable expenditure of Rs. 1.14 crore due to
injudicious split of work
The Company awarded the work to two parties instead of
awarding to the lowest tenderer which resulted in avoidable extra expenditure of
Rs. 1.14 crore.
Bharat Heavy Electricals Limited (Company) received
(September 1997) a letter of intent (LOI) from Maharashtra State Electricity
Board (MSEB) for erection, testing and commissioning of 2 Nos. steam generator
(boiler) and steam turbine generator along with auxiliaries at Khaperkheda
Thermal Power Station (two units of 210 MW each) of MSEB. The units were to be
commissioned within 33 months and 39 months respectively from the date of LOI.
For sub-contracting the execution of the above work, the
Company initiated the process on 18 February 1998 and decided on 8 June 1998 to
invite limited tenders from five selected parties against the normal procedure
of open tendering for such high value contracts. In the process, the Company
took about 9 months from the date of LOI in deciding the procedure for selection
of the sub-contractor.
Limited tender enquiries were issued to the five parties in
July 1998 and the price bids were opened in August 1998. While M/s. UB
Engineering Limited (UBE) was the first lowest at Rs. 17.40 crore for two units,
M/s. Larsen and Toubro Limited (L&T) stood at the second position at Rs.
17.91 crore. For one unit, they quoted rates of Rs. 9.56 crore and Rs. 9.46
crore respectively. Thus a discount of Rs.1.72 crore and Rs.1.01 crore
respectively was available if the Company awarded the work relating to both the
units to a single contractor. However, instead of taking advantage of discount
and awarding the work to the lowest tenderer, the tender committee proposed to
award work relating to a unit each to UBE and L&T.
After negotiations, the Company awarded the works to UBE in
September 1998 and L&T in December 1998 at the negotiated price of Rs. 9.27
crore each (i.e. at a total cost of Rs. 18.54 crore for two units) thereby
incurring an avoidable expenditure of Rs. 1.14 crore over and above the lowest
bid price of Rs.17.40 crore.
The Management stated (July 2000) that the order was divided
with a view to complete the works within the stringent time schedule and to ward
off any labour problem. The contention of the Management is not tenable as UBE
had quoted for both the works and therefore, ready to complete the work of both
the units within the stipulated time. As regards apprehension of labour
problems, the problem was universal and could happen with any contractor.
Besides, the purpose of splitting the order was defeated as the work awarded to
UBE could be completed in January 2001 against the schedule of July 2000 and the
other work awarded to L&T was yet to be completed (May 2001), against the
schedule of October 2000.
Thus injudicious splitting of order resulted in avoidable
extra expenditure of Rs. 1.14 crore.
The matter was referred to the Ministry in January 2001;
their reply was awaited (October 2001).
13.1.5 Avoidable expenditure of Rs.78.35 lakh due to procurement of valve
casting on single tender basis
The Company continued to procure valve castings on single
tender basis since 1995-96 instead of inviting open tender enquiry. In March
2000 when it did invite quotations from five suppliers, it received the much
lower rate as compared to the earlier ones. As a result, it incurred an
avoidable expenditure of Rs.78.35 lakh during 1998-99 and 1999-2000.
Industrial Valve Plant, Goindwal of Bharat Heavy Electricals
Limited (Company) had generally been procuring conventional valve casting as a
prime raw material for production of industrial valve on single tender basis
from M/s. Upper India Special Casting Limited, Ludhiana (UISCL) since 1995-96.
In July 1997 the Company issued advertisement in newspapers
for enlistment of suppliers of various items including valve casting. Though one
party was meeting the requirement, the Company continued to place orders on
UISCL on single tender basis during the period from 1997-98 to 1999-2000 at the
rate of Rs. 49.25 per kg, Rs. 52.50 per kg and Rs. 50.50 per kg respectively.
In March 2000 when the Company invited quotations for supply
of valve castings from five parties, it was able to get the competitive rate of
Rs. 39.90 per kg. Accordingly, the supply orders were placed on M/s. Rattan
Engineering Corporation Private Limited, Bhiwadi (RECPL), M/s. Saurabh Metals
Private Limited and M/s. Mittal Udyog (MU) at the rate of Rs.39.90 per kg for
the year 2000-2001. In fact, out of these three suppliers, the Company knew
RECPL and MU earlier.
Thus, due to not exploring and developing alternative
sources, the Company could not avail the benefit of competitive rates prior to
March 2000. Even by taking the indicative rate of Rs.39.90 per kg, the Company
could have saved at least Rs.78.35 lakh on the procurement of casting during the
years 1998-99 and 1999-2000 as given below:
Years |
Quantity of casting procured (in Kgs) |
Rates
(Rs. per Kg.) |
L-1 Rates
of 2000-2001 (Rs.) |
Difference
in rates (Rs.) |
Extra expenditure
(Rs. in lakh) |
1998-99 |
325345.67 |
52.50 |
39.90 |
12.60 |
40.99 |
1999-2000 |
352435.00 |
50.50 |
39.90 |
10.60 |
37.36 |
Total |
78.35 |
The Management stated (March 2001) that they explored the
possibilities of identifying and developing potential vendors in the northern
India since 1991. As a result of such efforts, M/s. Rine Engineering Private
Limited (REPL), MU and UISCL were identified as potential suppliers. However,
REPL was not considered due to lack of competence and quality and the product of
MU was not IBR (Indian Boiler Regulations) approved at that time.
The reply is not tenable as REPL had supplied the valve
castings during 1995-96 and 1996-97 and could have been developed as potential
supplier and MU had got IBR* approval in August 1997 from the Central Boiler
Board. Further, the order for the year 2000-01 was placed on RECPL with whom the
Company had been in touch since 1991.
Thus, the Company was purchasing valve castings on a single
tender basis since 1995-96 and during the period 1998-99 and 1999-2000 alone,
incurred an avoidable extra expenditure of Rs.78.35 lakh. The Company could
avail the benefit of competitive rates since March 2000, when they invited
quotations for procurement of valve castings.
The matter was referred to the Ministry in December 2000;
their reply was awaited (October 2001).
13.1.6 Loss of Rs.50.87 lakh due to despatch of Motors without receipt of
advance payment
The Company despatched the motors without obtaining the
balance payment of Rs.32.72 lakh in terms of the purchase order. As the
payment had not been received even after 4 years, the Company suffered a loss
of Rs. 50.87 lakh including loss of interest of Rs.18.15 lakh.
The Company received (January 1996) an order from M/s. Rohini
Strips Limited (RSL) New Delhi (a private party) for supply of 3 Nos. 500/730 KW
DC motors for their Gwalior Project at a total price of Rs.35.50 lakh (excise
duty and other taxes extra) with contractual delivery of July/August 1996. As
per terms of payment 25 per cent advance was to be released against purchase
order and balance 75 per cent payment alongwith duties and taxes against
proforma invoice before despatch of equipment.
The Company received Rs.13.00 lakh in April 1996 as advance
but despatched the motors in March 1997 and May 1997 without obtaining the 75
per cent of balance payment (Rs.32.72 lakh) including excise duty and Central
Sales Tax in contravention of the terms of the purchase order. The balance
payment had not been received so far (May 2001).
The Ministry while accepting (May 2001) the facts stated that
the motors were despatched violating the terms of the purchase order and there
was no approval in the file for the despatch. The Ministry further stated that
the case was being investigated by CBI and legal action had also been initiated
against the customer in the court.
Thus, the Company suffered a loss of Rs.50.87 lakh (Rs.32.72
lakh plus interest of Rs.18.15 lakh) due to despatch of motors without receipt
of the balance payment in accordance with terms and conditions of purchase
order.
Heavy Engineering Corporation Limited
13.2.1 Imprudent investment in non-performing assets
Infructuous expenditure of Rs. 3.36 crore on manufacturing of
Computerised Numerical Control lathes during 1997-98, lying idle with the
Company.
HEC decided to manufacture 4 Computerised Numerical Control (CNC)
special purpose lathes at an estimated cost of Rs.5.70 crore in July 1997. The
aim was to overcome the low technological capabilities of existing
medium-capacity lathes in the production shops of Heavy Machine Building Plant (HMBP).
The new lathes were supposed to replace 12 conventional lathes from the
production shops, provide additional time of 21872 hours and generate increased
out turn of Rs.6 crore per year. The scheme projected a pay back period of 5
years and internal rate of return (IRR) of 40 per cent.
Scrutiny of the records of the Company during 1999-2000
revealed that:
- 3 CNC lathes were manufactured at a cost of Rs.3.36 crore
during 1997-98, but remained to be commissioned until 2000-2001. The
proposal to manufacture the CNC lathes was not based on the actual numbers
of orders in hand;
- The first CNC lathe was installed in HMBP in August 2001
and was still under trial run. The second and third lathes had been modified
into general-purpose lathes. Of these, one was in the process of erection
and commissioning. None of the lathes had been utilised till date (September
2001); and
- The capital fund of Rs.3.36 crore spent in manufacturing
of these three CNC lathes by 1997-98 remained blocked for the last three
years. This resulted in consequential interest burden of Rs.1.41 crore.
The Ministry stated (September 2001) that there was no
facility available for profile-turning, coning and thread-cutting in any of the
existing machines which required high accuracy and surface finish. HMBP did not
possess any CNC lathe and the existing conventional lathes had lost their
accuracy and rigidity due to their continuous use for more than three decades.
The requirement of specific purpose CNC lathes had been projected based on the
market demand of plant and equipment from steel, mining and other core sector
industries. It added that the accuracy and surface finish required in certain
special equipment could not be achieved with existing conventional lathes and
could only be achieved by the use of CNC lathes where accuracy in microns (10/6
meter) could be achieved. The Ministry admitted that the orders as anticipated could
not be procured.
The contention of the Ministry is not acceptable in view of
the following:
- The utilisation of existing facilities in 1996-97 was
only 43.26 per cent to the total available hours, which gradually declined
to 33.66 per cent in 2000-2001;
- Even upto July 2001, the Company had received orders only
for four numbers of 5 cubic meter shovels from Coal India Limited, which
were being executed with the existing conventional lathes; and
- The projected payback period of 5 years and IRR of 40 per
cent was incorrect. Further, the so-called market demand was not adequately
tapped by effective marketing. As such, the stated objective of replacing
conventional lathes by the CNC lathes remained defeated.
Thus, the expenditure of Rs.3.36 crore spent by the Company
on manufacture of 3 CNC lathes had become infructuous besides increase in
interest burden to the extent of Rs.47 lakh per annum.
13.2.2 Irregular payment of excise duty
The Company paid excise duty in advance of sales, which led
to a loss of interest to the extent of Rs. 92.19 lakh.
HEC was declared sick and referred to the Board of Industrial
and Financial Reconstruction (BIFR) in February 1992. BIFR sanctioned (August
1996) a rehabilitation scheme for the Company and the same approved by the
Government of India in February 1997. This scheme provided the Company, inter
alia, financial relief in the form of equity, interest free non-plan loans,
deferment of sales tax dues, working capital facility at concessional rates.
Audit of Company’s records revealed that it had paid excise
duty in advance to the extent of Rs.13.46 crore, detailed as under:
(Rs. in crore)
Year |
Excise duty paid |
Sales accounted for without actual despatch of goods |
1998 |
3.74 |
31.42 |
1999 |
5.71 |
40.22 |
2000 |
4.01 |
28.48 |
Total |
13.46 |
100.12 |
In these cases, (a) the goods worth Rs. 13.79 crore remained
to be despatched upto March 2000, although excise duty had been paid in advance
in 1998 and 1999; and (b) the goods had been despatched only after a delay
ranging from 1 to 12 months. The Company, had, however, treated the goods as
sold on the date on which excise duty was paid.
This treatment of sales was commented upon on the accounts of
the Company for the year 1999-2000. Following this, the Company terminated its
policy of including such sales in their accounts of 2000-2001. Further, Central
Excise Rules require that excise duty is payable at the time of removal of goods
from the Company premises.
Thus, by making unnecessary payment of excise duty in
advance, that too at the time when it was in a severe financial crunch, the
Company lost interest thereon to the extent of Rs. 92.19 lakh. Aside of this
loss, the Company appeared to have deliberately inflated sales during the
aforesaid period and was also against the Company’s Accounting Policies which
provides that ‘sales are recorded when significant risks and rewards of
ownership are transferred to the customers’.
The Management accepted (June 2001) the facts of the case and
admitted the deficiency in the prevailing system. It further stated that the
practice, however, had been discontinued since April 2000 and excise duty was
being paid only on items which were despatched by 31 March of the financial
year.
The matter was referred to the Ministry in April 2001; their
reply was awaited (October 2001).
HMT (International) Limited
13.3.1 Blocking of funds
The Company failed to obtain adequate securities for Rs. 2.18
crore advanced to three suppliers for exports. The Company could get back only
Rs.56.15 lakh resulting in blocking of funds of Rs.1.62 crore and loss of
interest of Rs.56.30 lakh. The cases against all the three suppliers were
pending before the Court of Law for adjudication.
With a view to increase the export turnover and better
profitability, HMT (International) Limited (Company) entered into four
agreements with three suppliers as per details given below.
Sr. No. |
Name of the supplier |
Period |
Export items |
1. |
Nucor Wires Limited Bangalore (NWL) |
February 1997 |
Flux cored wire and Welding fluxes |
2. |
Kuluthara Exports Limited Aroor (KEL) |
January 1997 and April 1997 |
Marine products |
3. |
Nawab Cashew Packers, Kollam (NCP) |
December 1997 |
Cashew products |
The Company accepted undated cheques and equity shares as
collateral securities for Rs.2.18 crore advanced to the three suppliers. The
Company did not lay down any policy for extending such export credits.
The shipping documents tendered by NWL were found to be
defective and hence the overseas purchasers rejected the goods. NWL subsequently
sold partial quantity to other purchaser and the residual quantity was lying at
Dubai Port (June 2001). Hence the Company could realise Rs.53.15 lakh from the
NWL against an advance of Rs.80 lakh. NCP and KEL did not meet the export
obligation and hence the Company insisted November 1998 and April 1999
respectively upon the repayment of the amounts advanced. However, the Company
could realise from NCP Rs.3 lakh against an amount of Rs.38.40 lakh advanced.
The Company could recover nothing from KEL to whom Rs.1 crore was advanced. The
cheques offered as collateral security by the suppliers were dishonoured on
presentation. The Company, thereafter, filed criminal cases against the three
suppliers which were pending in the Court (June 2001).
The Management stated (March 2001) that policy of obtaining
securities for advance and its recovery required to be viewed in the context of
the type of agreements entered into with the suppliers in respect of execution
of export orders for a specific product. The reply is not tenable as the
securities obtained by the Company proved to be insufficient to protect its
interest.
Failure to obtain securities encashable on demand like bank
guarantees particularly in the field of export of commodities resulted in
blocking of funds amounting to Rs.1.62 crore, entailing loss of interest
amounting to Rs.56.30 lakh as of March 2001.
The matter was referred to the Ministry in April 2001, their
reply was awaited (October 2001).
|