CHAPTER 17
MINISTRY OF POWER
National Hydroelectric Power Corporation Limited
17.1.1 Loss of generation of power
Due to failure in ensuring availability of critical spares
and equipment in working condition, the Company could not operate one of the
three units of its Chamera Project resulting in loss of generation of power.
Thus, the Company incurred a loss of revenue amounting to Rs. 14.58 crore,
besides loss of incentive amounting to Rs. 24.77 crore.
Chamera Hydroelectric Project, Stage -I (Project) of 540 MWs
(three units of 180 MWs) was commissioned by National Hydroelectric Power
Corporation Limited (NHPC) in April 1994. One of the units of the Project could
not generate power on two occasions during 1996-97 and 1998-99 to 1999-2000 due
to the failure of the Management in keeping critical spares and equipment in
working condition. As a result, the Company incurred a loss of revenue amounting
to Rs. 14.58 crore, besides loss of incentive of Rs. 24.77 crore. These two
cases are discussed below:
Case (A)
On 5 February 1996, one of the units tripped due to gas
leakage owing to failure of a gas tight bushing. Although spares required for
replacement of the failed bushing were mandatory in nature and should have been
kept in store as stand by, the Company did not ensure the availability of the
mandatory spares in working condition. In fact, the consignment of original
equipment along with spare bushing was received by the Company in soaked
condition for which insurance claim was also lodged. However, the package
containing spare bushing was not opened at the time of receipt. After arrival of
the engineers of M/s. Siemens, Canada at site on 3 April 1996, the package was
opened and spare bushing was not found fit for use.
Accordingly, NHPC had to place order for supply of the same
on M/s. Siemens on 16 April 1996. On receipt of the bushing on 7 May 1996, the
generating unit was synchronised with the grid on 12 May 1996. Even though
sufficient quantity of water was available from 16 April 1996 to 12 May 1996,
the unit could not generate power owing to non-availability of the critical
spares. This resulted in loss of generation of 46.81 MUs, entailing loss of
revenue amounting to Rs. 10.11 crore.
The Management stated (June 2001) that mandatory spares were
kept in sealed condition as per the manufacturer's instructions and were opened
only after arrival of the representatives of the manufacturer.
The reply is not tenable, as the initial spares arrived in
wet condition for which insurance claim was also lodged by NHPC. Thus, the
Company was aware that the initial spares were not in usable condition and as
such should have ensured the availability of critical spares.
Case (B)
The project generates power at 13.8 KV, which is further
stepped upto 400 KV level by a transformer for feeding the grid. The project had
ten transformers each of 75 MVA capacity including one spare transformer. One
transformer of a unit failed due to internal fault in its winding on 30 December
1997 and was replaced by a spare transformer. The unit was re-commissioned on 17
January 1998.
For repair of the defective transformer, matter was taken up
with M/s. Pauwels, Canada. In July 1998, NHPC also issued purchase requisition
to procure one additional transformer from M/s. Pauwels, ignoring the offer (24
January 1998) of Bharat Heavy Electricals Limited (BHEL). However, the Company
could neither get the defective transformer repaired, nor procure the new one
due to non-finalisation of the inspection charges demanded by M/s. Pauwels.
Meanwhile, another transformer developed internal fault on 30
March 1999. This time, the Company managed to get one defective transformer
repaired from BHEL by cannibalising winding of another defective transformer and
re-commissioned the unit on 16 June 1999. Subsequently, it also placed an order
(21 June 1999) on BHEL for supply of additional transformer.
Consequently, one unit of the project could not be operated
during the period from 30 March 1999 to 15 June 1999, due to non-availability of
a transformer even though there was demand in the grid and sufficient water
level in river. This resulted in loss of generation of 15 MUs causing avoidable
revenue loss of Rs. 4.47 crore to the Company. Besides, it also lost incentive
of Rs. 24.77 crore which it could have earned on account of availability of
installed capacity above the normative level of 90 per cent.
The Management stated (June 2001) that it was a normal
practice to purchase the transformer from the original equipment manufacture and
repair of the defective transformer could not materialise due to dispute on the
increase of Rs. 3.10 lakh in inspection charges demanded by M/s. Pauwels. They
further, stated that BHEL was not in a position to repair the defective
transformer for want of certain data relating to specifications, design, etc. of
the transformer.
The reply is not tenable, as even after lapse of more than 15
months from the incident of first fault on 30 December 1997, the Company could
not ensure the availability of one spare transformer despite the knowledge of
high fluctuation of voltage in the grid. Further, BHEL was ready to supply the
new transformer in January 1998 and ultimately, supplied the same in January
2000. If the Company approached BHEL for supplying the new transformer in
January 1998 itself, it could have avoided the loss of revenue of Rs. 4.47 crore
and loss of incentive of Rs. 24.77 crore.
The matter was referred to the Ministry in April 2001; their
reply was awaited (October 2001).
|