CHAPTER 2
MINISTRY OF CHEMICALS AND PETROCHEMICALS
Indian Petrochemicals Corporation Limited
2.1.1 Extra expenditure on procurement of chemical
Due to delay in testing the suitability of chemical from an
alternative cheaper source of supply, IPCL incurred an extra expenditure of
Rs. 1.30 crore on procurement of chemical from another source at a higher
rate.Indian Petrochemicals Corporation Limited (IPCL) invited
(June 1997) limited tenders to procure 18.75 MT of ‘PEPQ’ (antioxidant) for use
in its Vadodara Plant. Out of the two offers received, the offer of M/s. GE
Plastics India Limited, a unit of Specialty Chemical Division of General
Electric Plastics, Netherlands (GEP) was lower (L1) at the landed cost of Rs.
7.91 lakh per MT as compared to the offer of M/s. Hindustan Ciba Geigy (regular
supplier) of Rs. 13.82 lakh per MT (L2). IPCL placed an order (July 1997) for
12.75 MT on M/s. Hindustan Ciba Geigy and decided to reserve 6 MT for ordering
on GEP, subject to suitability of the material to be tested. In November 1997,
IPCL invited one more tender for procurement of 22 MT of chemical, against which
both the firms again quoted the same rates of June 1997. No document was on
record to indicate that the GEP was ever asked to submit the samples for test.
Since IPCL had not received the sample against the first order from GEP and
tested its suitability, the second order was also placed (January 1998) on M/s.
Hindustan Ciba Geigy at an additional cost of Rs. 1.30 crore as compared to the
rates of GEP.
The Management could obtain the sample from GEP only in
January 1998 (though the decision was taken in July 1997) and its test
suitability was established in February 1998. Accordingly, purchase order for
the reserved quantity of 6 MT of chemical was placed on GEP in April 1998. Thus
the delay in obtaining the sample and establish its suitability resulted in
procurement of chemical at a higher rate by incurring an extra expenditure of Rs.
1.30 crore.
On this being pointed out in Audit, the Management stated
(June/August 2000) that the orders could not be placed on GEP as it had
submitted the sample very late. Therefore, the requirement of material was met
by placing the purchase order on M/s. Hindustan Ciba Geigy again, being proven
and established vendor. Further, the process of establishing reliable and
qualitative source of supply was expected to take time.
The reply of the Management is not tenable in view of the
fact that there was nothing on record to show that the Company took up the
matter with the lowest quoted party to get the sample tested at the earliest so
as to avail of the lower price benefit. Besides, the system of placing trial
order for new product generally followed by IPCL in similar cases was also not
followed in the instant case.
The Ministry stated (March 2001) that ‘PEPQ’ had direct
effect on the quality of the finished products and the particular supplier was
already approved for this new plant, as such the Company had to weigh all the
factors before switching over to the new suppliers. The Ministry, however,
admitted that in view of the price gap of about Rs. 6.00 lakh per MT in the
material of the two suppliers, IPCL could perhaps have shown some urgency in
testing the material offered by GEP.
2.1.2
Infructuous expenditure on the purchase of heat
exchanger
Despite the knowledge of the fact that the higher capacity heat
exchanger was to be installed in Train I of the plant at Nagothane, IPCL
went ahead in procuring another lower capacity down stream heat exchanger
costing Rs. 69.49 lakh. Consequently the heat exchanger could not be put to
use and was lying idle.High Density Poly Ethylene (HDPE)/Low Linear Density Poly
Ethylene (LLDPE) plant in Maharashtra Gas Cracker Complex, Nagothane of IPCL
comprises Train I and II, each of which contains upstream and down stream
coolers. The down stream coolers installed in both the trains were found
(November 1993) to be in an unhealthy conditions due to thinning of their tubes
and occasional leakage. In order to replace these coolers, the Management
decided to procure two heat exchangers one for each Train and an order for one
heat exchanger was placed (September 1994) on M/s. Godrej & Boyce Limited (Godrej).
The heat exchanger received in February 1996 was installed on Train II in May
1997 during the normal shut down of Gas Cracker Plant.
Meanwhile in June 1995, IPCL approved an expansion scheme for
LLDPE wherein downstream heat exchanger of higher capacity and of modified
version was to be installed in Train I. Despite this fact on record, IPCL
proceeded ahead to procure one conventional down stream heat exchanger for Train
I and placed an order on M/s. Mistry Prabhudas Manji Engineering Private
Limited, Mumbai (MPM) on 26 December 1995 at a cost of Rs.74.61 lakh. The
downstream heat exchanger was to be supplied by August 1996 but was actually
supplied in September 1998 (i.e. after over a period of two years of the
scheduled delivery date). The main reason for this abnormal delay was that the
firm was financially unsound. Considering the financial difficulties of the MPM,
IPCL in violation of the terms of purchase order paid (March 1997) an interest
free advance of Rs. 23.20 lakh. The advance was paid with a specific condition
that the delivery would be made by April 1997 failing which the order was to be
cancelled and the advance refunded along with interest at the rate of 24 per
cent. Despite this, MPM failed to adhere the delivery schedule and IPCL neither
cancelled the order nor recovered the advance with interest as stipulated.
Meanwhile in line with the proposed expansion plan, IPCL
placed another order for the supply of higher capacity downstream heat exchanger
on M/s. Samsung Engineering Company Limited (Samsung) on 17 January 1997 for the
same Train I. A committee of officers of IPCL while reviewing the progress made
in the order placed earlier with MPM observed on 18 March 1997 that the down
stream cooler of a larger capacity under proposed expansion scheme was scheduled
to be installed by Samsung in the first quarter of 1998 and therefore,
replacement of down stream cooler with one supplied by MPM in Train I after
April 1997 shutdown and before first quarter of 1998 would hardly serve any
purpose. Subsequently, another committee of officers in their report of 10
December 1997 further reiterated that there was no possibility of a shutdown
before April 1998 to replace the exchanger fabricated by MPM. The newly
fabricated exchanger by MPM would, therefore, become redundant and its cost
would be infructuous and the committee proposed that the exchanger might not be
accepted and necessary action be initiated for the recovery of the advance paid
to the firm.
The heat exchanger supplied by Samsung was installed in Train
I in May 1998. Instead of cancelling the order on MPM, IPCL decided in April
1998 to convert the down stream heat exchanger ordered on MPM into up stream
with suitable modifications and keep it as insurance spare. The heat exchanger
subsequently supplied by MPM in September 1998 at a cost of Rs. 69.49 lakh was
lying idle (May 2001).
The Management replied (February 2001) that the performance
of both the downstream gas coolers deteriorated at a faster rate, resulting in
heavy production loss. To improve productivity in future, the second downstream
gas cooler was ordered in December 1995 but MPM could not complete the order by
due date. Subsequently it was decided that if the exchanger was ready by April
1997 it could be gainfully utilised till the installation of new exchanger by
Samsung. However, the MPM could not meet this delivery schedule also. In view of
this it was decided to have it as insurance spare to install as upstream cooler
after carrying out few modifications whenever required.
The Management further added (May 2001) that in view of delay
in delivery by MPM the options left with them were either to cancel the order
and initiate legal action to recover the advance paid or to explore the
possibilities of utilising the exchanger being a tailor made long delivery item.
Both these options were deliberated and option regarding cancellation of order
was ruled out since the litigation would have been time consuming and may not
lead to IPCL’s advantage. Regarding recovering of liquidated damages for the
delay in supply the Management stated that the damages recoverable worked out to
Rs. 5.80 lakh and against this Rs. 6.95 lakh had been recovered by way of cost
of modification for converting the heat exchanger to upstream cooler. Therefore
it was decided not to levy any further charges against the firm.
The replies of the Management are not tenable on the grounds
that with the installation of the two downstream coolers by Godrej and Samsung,
two old heat exchangers were available which could have been reused by re-tubing
them with filter tubes. The breach of contract by not supplying the exchanger as
per the agreed terms was committed by MPM as such the apprehension of the
Management that the litigation may not led to IPCL’s advantages was not based on
any sound logic. Thus, decision of the Management to accept it, as insurance
spare was a fait accompli and after thought. Further had the heat
exchanger been supplied by MPM by delivery date of August 1996, the loss of
production as stated by the Management could have been avoided for the period
from May 1997 to May 1998 (date of installation of exchanger by Samsung).
The matter was referred to the Ministry in March 2001; their
reply was awaited (October 2001).
2.1.3 Undue financial benefit to a private firm
IPCL released the payment to a firm on the basis of minimum
guaranteed offtake quantity from the date of commissioning of the pipeline
rather than from the first day of the month following the date of
commissioning as envisaged in the agreement. This resulted in an extra
payment of Rs. 67.60 lakh to the firm.IPCL entered into an agreement with M/s. Dodsal Limited (DL)
on 8 December 1995 for laying and operating of Dehaj - Gandhar - Baroda
pipelines on build, own, operate and transfer basis. The pipelines numbering
three were intended for product transfer of Ethylene, Propylene and Naphtha. The
minimum guaranteed offtake (MGO) for product transfer was fixed at 240000 MT
per annum (i.e. 20000 MT per month). For this purpose, Clause 5 (b) (3) of
the agreement stated that the first year of operation would start from the first
day of the month following the date of commissioning and subsequent years shall
start from its anniversary.
The pipeline for product transfer of Propylene was
commissioned on 23 May 1997 and 526 MT of Propylene was transferred between 23
May 1997 and 31 May 1997. For the purpose of calculation of compensation, the
month was reckoned from 23 May 1997 to 22 June 1997. This principle was applied
further from 23 June 1997 till 22 March 1998 and payments for 20000 MT being MGO
per month were made by IPCL to DL. In addition, Rs. 74.10 lakh was paid by IPCL
for pro rata MGO of 6000 MT for remaining 9 days from 23 March 1998 to 31
March 1998. Thereafter the payment was made on the basis of calendar months.
In terms of the agreement the payment on the basis of MGO was
to commence from 1 June 1997 onwards and not from 23 May 1997. For the initial
product transfer of 526 MT Propylene between 23 May 1997 and 31 May 1997, IPCL
was to pay Rs. 6.50 lakh (Rs.1235 per MT) only, whereas it paid Rs. 74.10 lakh. This resulted in undue financial benefit to the firm to the tune
of Rs. 67.60 lakh.
The Management admitted (April 2001) that there was no
ambiguity in clause 5(b) (3) of the agreement for the purpose of monthly MGO
rate. DL should have raised separate bill for the period from 23 May 1997 (date
of commissioning) till the end of month and the calculation of the minimum
offtake of 240000 MT per year start from the month following the date of
commissioning i.e. 1 June 1997. DL, however, preferred to raise monthly bill
linked to the date of commissioning i.e. 23 May 1997 for the monthly MGO or
actual whichever was higher. The Company did not object, as the same was not
considered disadvantageous with reference to the contractual obligations
accepted under the contract.
The Ministry further added (July 2001) that IPCL had to make
payment for 9 days of May 1997 also as per the MGO clause which came to 6000 MTs
(prorated MGO). Accordingly, the payment amounting to Rs. 74.10 lakh was
made to DL since the period from 23 May 1997 to 31 May 1997 was also a part of
the contract of 15 years which would expire on 22 May 2012.
The replies of the Ministry and the Management are not
tenable as there was no contractual obligation to pay on the basis of MGO for
the period from 23 May 1997 to 31 May 1997 in terms of clause 5 (b) (3) of the
contract and the payment should have been restricted to actual quantity
transferred.
|