CHAPTER 4
MINISTRY OF COAL
Bharat Coking Coal Limited
4.1.1 Loss of Rs. 14.24 crore due to shortages of process rejects in Moonidih
Washery
An unaccounted shortage of 5.75 lakh MT of process rejects
caused a loss of Rs. 14.24 crore to the Company.
Process rejects generated in washeries during washing of raw
coal are saleable products. In Moonidih Washery of Bharat Coking Coal Limited
(Company), the stock of process rejects was being regularly verified by the area
Management.
In May 1996, when the stock was physically verified as on 31
March 1996 by a team of Coal India Limited, the book stock of rejects as on date
was changed from 12.82 lakh MT to 7.07 lakh MT. There was a variation of 5.75
lakh MT because the quantity of rejects despatched was reflected as 6.13 lakh MT
in the report of annual measurement of saleable stock as on 1 April 1996,
whereas quantity of rejects actually despatched came to only 0.38 lakh MT as per
the washery’s statement.
There was no documentary evidence to demonstrate how 5.75
lakh MT of rejects had been used outside washery premises. The shortages
resulted in a loss of Rs.14.24 crore (5.75 lakh MT @ Rs.247.71 per MT).
The Management stated (November 1999) that the stock of 5.75
lakh MT rejects was dumped outside the washery premises using departmental
transport. These had been used for levelling a stadium and for levelling and
filling up roads, wall and ponds. It stated that it was not possible to measure
the process rejects due to non-availability of ground contours.
The Management’s reply is unacceptable, as they had been
unable to produce any documentary evidence in support of their claim of having
used the rejects for different purposes as stated in reply vis-à-vis failure of
measurement of process rejects.
It is not possible to accept the contention that rejects
valued at Rs. 247.71 per MT were utilised as filling up material as against the
normal practice of using earth for such purposes being the far cheaper
alternative.
The matter was referred to Ministry in May 2000; their reply
was awaited (October 2001).
4.1.2 Excess consumption of material
The consumption of Magnetite used in the process of washing
the coal was in excess of the envisaged norm in 5 out of 7 washeries of the
Company resulting in excess consumption of 0.41 lakh MT of Magnetite valued at
Rs. 5.01 crore for the period from 1995-96 to 1999-2000.
Magnetite is used as solution for separation of clean coal
from refuse by Float and Sink method. A major part of material is recovered,
reprocessed and reused. Bharat Coking Coal Limited (Company) had fixed norm for
consumption of Magnetite separately for each of the 7 washeries for the period
between 1966 and 1988. The norm varied from 0.5 Kg to 1.5 Kg per tonne of raw
coal washed.
The Company constituted (September 1995) a High Level
Committee to review of norm of consumption of Magnetite keeping in view the
ageing of the washeries and other constraints. On the basis of recommendation of
the Committee, the norm was revised upward to 0.97 Kg and 3.5 Kg per tonne of
raw coal washed.
A review of consumption pattern of Magnetite for the years
1995-96 to 1999-2000 revealed that in spite of upward revision of the norms,
actual consumption continued to be higher than the revised norm in 5 out of 7
washeries of the Company. The percentage of excess consumption over the revised
norm for the above period ranged from 3 to 226 per cent. This resulted in excess
consumption of 0.41 lakh MT of Magnetite valued at Rs. 5.01 crore for the same
period.
The main reasons for the excess consumption were absence of
proper upkeep and maintenance of equipment leading to inefficient operation of
Ball Mills and Magnetite separators and leakage in pipe lines, pumps and sumps
and lack of awareness amongst the workers about wastage of valuable material.
The Management replied (September 2000) that the Committee
fixed certain ideal norms of consumption and unless all assumptions were set out
it was not possible to achieve the norm in real operation. It also stated that
to a great extent the objectives (of containing excess consumption of Magnetite)
had been achieved. The Ministry reiterated (October 2001) the views of the
Management.
The reply is not tenable in view of the fact that despite the
upward revision of norms, consumption continued to be high. The Company also
maintained that higher consumption of Magnetite could be attributed to the
necessity of maintaining strict control over the quality of the washed coal. In
reality, the Company continued to face deductions for poor quality of the coal
supplied to customers and there was no record to prove that this was a conscious
decision.
Thus, due to lack of proper upkeep of the equipment and
control over the consumption of Magnetite, the Company suffered a loss of Rs.
5.01 crore due to excess consumption of the same for the period from 1995-96 to
1999-2000.
4.1.3 Loss due to inundation of a quarry
Lack of adequate planning in the construction of an
embankment to prevent seepage of water into a quarry led to its inundation
resulting in a loss of Rs.74 lakh to the Company.
The Jhilia Nala passes on the western boundary of New Liakdih
Open Cast Project (NLOCP) of Bharat Coking Coal Limited (Company) from north to
south. The Nala carries catchment water from up stream areas during rainy
season. In order to prevent water flowing/seeping into the quarry during rainy
season, overburden from the quarry was being dumped regularly between the Nala
and the quarry to act as embankment.
As advised by Director General (Mines Safety), the Company on
30 May 1998 awarded to three contractors the work of construction of embankment
all along the Nala to a length of 200 metres as a permanent measure. The aim was
to strengthen the embankment and prevent the quarry from being inundated with
water from the Nala. It awarded the work to contractors with no experience in
execution of flood protection works. Although the Company stipulated one month’s
time for completion of the work, it delayed releasing the work order and
drawings to the contractors. Consequently, the contractors left the work
incomplete on 12 July 1998. By this time about 75 per cent of the work was
completed.
In August 1998 the Nala overflowed due to rains which, in
turn, led to heavy seepage of water beneath the partially constructed
embankment. Hence the quarry was flooded with rainwater. Not finding de-watering
feasible, the Company finally abandoned the quarry in September 1998.
As a result of inundation and the consequent abandonment of
the quarry, equipment valued at Rs. 7 lakh and coal stock on the quarry bed
valued at Rs. 7.65 lakh were lost. Besides coal reserves of 0.43 lakh MT valued
at Rs. 52.75 lakh (net realisable value) were rendered irrecoverable. As per the
claim made by the contractors, the value of work done was Rs. 6.58 lakh.
The Ministry inter alia stated (August 2001) that the
inundation of the quarry was an instance of force majeure and beyond its
control though precaution was taken well in advance.
The reply is not tenable for the following reasons:
- the Company awarded the work to contractors with no
experience in execution of flood protection works. The works were taken up
during monsoon season, that too without obtaining the drawings in advance;
- the contractors failed to carry out back filling of
the gap between the retaining wall and existing embankment after
construction;
- the contractors disturbed the existing embankment
with filled up overburden. This allowed seepage into and consequent
inundation of the quarry; and
- the Company delayed in giving regular drawings and
work order. This led to suspension of the work mid-way by the contractors.
Thus defective planning and faulty execution of work by
inexperienced contractors by the Company led to the inundation of the quarry and
consequent avoidable loss of Rs. 73.98 lakh being the value of equipment, coal
stock, coal reserves and cost of construction of embankment.
Coal India Limited
4.2.1 Avoidable payment of rail freight surcharge aggregating Rs 2.43 crore
Failure to ensure availability of sufficient fund in the bank
account before issue of credit note cum cheque to Railways towards payment of
freight and other charges resulted in avoidable payment of surcharge of Rs. 2.43
crore.
In terms of an agreement entered into in November 1992 with
North East Frontier Railway (NFR), Coal India Limited (CIL) avails of a “credit
note cum cheque” (CNCC) facility for payment of freight and other charges on the
traffic booked by it. Under this arrangement, CIL issues a CNCC drawn on a
designated bank in lieu of cash towards payment of freight and other charges for
the traffic booked from Rail Stations at Ledo, Lumding, New Bongaigaon,
Kamakhyaguri and Baragalai and New Guwahati. On receipt of CNCC the traffic is
booked on ‘paid basis’ by the Railways. In case the CNCC is dishonoured on
presentation, the traffic booked initially on ‘paid basis’ is treated as ‘to pay
basis’ and a surcharge at 15 per cent (10 per cent upto 14 January 1995) of
freight charges is levied. In order to ensure timely payment of CNCCs on
presentation by Railways, CIL was required to maintain sufficient funds
in the designated bank to honour the CNCCs issued.
Between March 1993 and March 1995, Railways presented CNCCs
aggregating to Rs. 22.66 crore issued by CIL towards payment of freight to the
designated bank (Central Bank of India, Guwahati). These were, however,
dishonoured, as CIL had not maintained sufficient funds in their bank account.
As a result, Railways treated the freight paid Railway receipts (RRs) as freight
to pay RRs and levied (May 1996) surcharge aggregating Rs. 2.43 crore. CIL paid
(April 1999 and March 2000) Rs. 1.85 crore in cash and Rs. 58 lakh by way of
adjustment against claims due to it. Railways also claimed (December 1999)
interest amounting to Rs. 53.44 lakh due to delay in payment of surcharge. Its
request for waiver of interest was pending with Railway Board.
The Company while accepting the facts of the case stated
(February 2001) that steps had since been initiated in CIL to ensure that no
such incidence is allowed to recur ever again.
The Company failed to establish proper mechanism to ensure
that its commitments towards payment of Railway freight are monitored and
honoured as and when these arise. By failing to ensure availability of
sufficient funds in the designated bank account, CIL incurred avoidable
expenditure aggregating to Rs 2.43 crore.
The matter was referred to the Ministry in March 2001; their
reply was awaited (October 2001).
Mahanadi Coalfields Limited
4.3.1 Loss of Rs. 1.09 crore due to delay in availing
concessional rate of electricity tariff available for colony consumption
Due to delay in making arrangements for separate metering of
colony consumption, the Company had forgone concessional rate of electricity
tariff to the tune of Rs. 1.09 crore.
Government of Orissa with effect from 2 April 1992 allowed 10
per cent concessional rate of tariff for domestic consumption of electricity
over industrial consumption provided that the units consumed for colony were
metered separately. This concession was withdrawn between 7 September 1993 and
20 May 1996.
The Orient Area of Mahanadi Coalfields Limited (Company) had
been using electricity for industrial as well as for colony consumption. As
there was no separate metering arrangement for colony consumption, the Area
Office continued to pay for colony consumption also at tariff applicable for
industrial consumption prior to 6 September 1993 and after restoration of
concessional tariff on 21 May 1996. The Orient Area had two separate connections
for colony consumption without separate metering arrangement. The Area Office
segregated the colony consumption and arranged separate metering of two service
connections to avail of the concessional rate of tariff for colony consumption.
However, this was done only from March 1998 and June 1998 respectively.
Thus, due to delay in installation of separate meters for
colony consumption the Company had foregone concessional electricity tariff to
the tune of Rs. 1.09 crore for the period from May 1996 to March/May 1998.
The Ministry while concurring with the observation of the
Audit indicated (December 2000) that it has taken a serious view of lack of
action before 1993 and after 1996 to avail concessional rate of domestic
consumption of electricity and advised the Company to enquire into the matter
and fix responsibility.
Neyveli Lignite Corporation Limited
4.4.1 Avoidable expenditure
The Company entrusted belt-reconditioning work to an outside
agency despite adequate in-house capacity for the reconditioning. This resulted
in avoidable expenditure of Rs.59.44 lakh.
Belt Reconditioning Plant (BRP) of Neyveli Lignite
Corporation Limited (Company) had an installed capacity of 12960 metres per
annum to recondition the used steel cord conveyor belts. The capacity of the
BRP was further augmented with commissioning of a new machine with capacity of
19440 metres in July 1997. Keeping in view the increase in curing time from 1.5
minutes per mm to 2 minutes per mm for improved quality, the total capacity of
the two plants was reassessed as 24300 metres per annum (90 metres per
day for 270 days/year) for all sizes up to 2400 mm width.
The Company estimated (November 1998) a total shortage of
reconditioned belts by 7398 metres for 1998-99 and 1999-2000 after taking into
account available stock of belts and performance of the BRP for the previous
year.
To meet the shortfall, the Company placed (June 1999) an
order with an outside agency for reconditioning of 800 metres of 2000 mm width
belt at negotiated rate of Rs. 9360 per metre as against Rs.4067 per metre being
the cost at which the Company was reconditioning the belts at BRP. The extra
expenditure due to off loading reconditioning work to outside agency was
Rs.59.44 lakh.
The records revealed that the proposal approved for
reconditioning work to outside agency, the Company did not take into account the
actual capacity of 24300 metres per annum of BRP. Also, the cost-benefit
analysis of internal reconditioning versus outsourcing was not made correctly.
The Management replied (October 1999/ July 2000) that the
capacity achieved by BRP in the past was taken into account after considering
the various ancillary systems on which the plant was dependent. They further
stated that the Company’s in-house reconditioning lasted only 8000 hours running
whereas the outside agency had assured 27000 hours running of their
reconditioned belts. The Ministry endorsed (August 2000) the views of the
Management.
The reply is not tenable, as BRP had reconditioned more than
the estimated quantity of belts during 1998-99 and 1999-2000. As against the
Company’s projected requirement of 15690 metres of 2000 mm width belt upto March
2000, 17194 metres were actually reconditioned during the same period, which was
more than the projected requirement. Thus, even after reconditioning more of the
belts than projected, BRP had sufficient spare capacity to recondition 800
metres of reconditioning work outsourced to an outside agency. Thus the
outsourcing of work was clearly not necessary and was avoidable. As regards to
the evidence on 27000 hours of satisfactory performance of reconditioned belts
the Company expressed inability to produce the same.
Thus, as a result of incorrect estimation and unjustified
outsourcing of reconditioning work, the Company incurred an amount of Rs.59.44
lakh, which was avoidable.
Northern Coalfields Limited
4.5.1 Avoidable expenditure on agency commission
The Company appointed an Agent for handling imported
consignments in spite of having an in-house clearing and forwarding
department to handle imported consignments resulting in an avoidable
expenditure of Rs. 2.16 crore towards agency commission.
The Northern Coalfields Limited (NCL) is one of the 8
subsidiaries of Coal India Limited (CIL). The CIL has a separate clearing and
forwarding (C&F) department to handle imports of all its subsidiaries. Except
NCL, all the subsidiaries of CIL route their imports through this department.
NCL utilised the services of C&F department for clearance of imported
consignments upto June 1992. NCL appointed M/s. Balmer Lawrie & Company Limited
(BLC) as their C&F agents initially for one year which was renewed for 8 years
upto July 2001 to handle imports on payment of commission at 0.5 per cent of CIF
value from 1 July 1992. This was done on the plea that the C&F department was
not able to do expeditious clearance of imported consignments.
NCL paid BLC Rs. 2.16 crore by way of agency commission
between 1992-93 and 2000-01. This payment could have been avoided largely had
the Company utilised the services of C&F department of CIL as was done by other
subsidiaries. The agreement with BLC had, however, been terminated with effect
from July 2001.
The Management while justifying the appointment of BLC as C&F
agent, stated (March 2001) that there had been inordinate delay in clearance of
imported consignments and the C&F department of CIL was not in a position to
cater to the need for expeditious release of consignment from the port.
The reply is not convincing because seven out of eight
subsidiaries were availing the services of C&F department of CIL without any
complaint and the C&F department is adequately geared upto accept the tasks of
all subsidiaries. Further the Company should have reviewed the strengths and
capabilities of C&F department of CIL, before extending the period of agreement
with BLC from time to time.
Thus, the expenditure of Rs. 2.16 crore incurred by way of
agency commission could have been avoided largely, if NCL had availed the
services of C&F department of CIL as was done by other subsidiaries.
The matter was referred to the Ministry in June 2001; their
reply was awaited (October 2001).
South Eastern Coalfields Limited
4.6.1 Infructuous expenditure of Rs. 93.40 lakh
Injudicious setting up of a Central Sales Centre without
carrying out any cost benefit analysis resulted in an infructuous expenditure of
Rs. 93.40 lakh.
South Eastern Coalfields Limited (Company) used to despatch
coal from Chhaal, Dharam and Mand underground mines to its consumers directly
from the pit-heads. In October 1992, it decided to set up a Central Sales Centre
(CSC) at Chhal block of Raigarh area to despatch coal produced from these mines,
without, however, envisaging any benefits therefrom. The Project Report (May
1993), also, did not mention any benefits arising from the setting up of the CSC
and no cost benefit analysis was carried out.
The construction of the CSC was completed on 5 May 1996 at a
total cost of Rs. 93.40 lakh. It, however, could not be operationalised till 1
August 1999 because of delay in completion of approach road and ramp of the CSC
and non-availability of a transformer for power supply. Meanwhile, one of the
three mines (Mand), expected to produce one third of the total coal to be sold
from CSC, was to be closed with effect from 1 November 1997 due to adverse
geo-mining conditions and poor quality of coal.
Even after the commencement of operation by the CSC, it could
not fetch business, as the consumers were reluctant to bear high dump charges of
Rs. 42 per tonne, being the cost of operation of the CSC. As a result, the sales
from the remaining two mines (Chhaal and Dharam) plummeted to almost half as
compared to the period prior to the operation of CSC. This eventually forced (30
September 2000) the Company to reduce the dump charges from Rs. 42 to Rs. 14 per
tonne, which was less than half of the cash cost of operation. This established
the futility of setting up of the CSC which remained idle for the first 39
months of its completion and thereafter, has not been able to recover even its
cash cost.
The Ministry admitted (March 2001) that the entire
expenditure of Rs. 93.40 lakh was not commercially justified and directed the
Company to fix the responsibility for the lapse. The Committee constituted by
the Company recommended (6 April 2001) closure of the CSC on the grounds that
the consumers were being charged extra without any value addition and space at
the CSC was restricted, which would always remain a constraint. However, it did
not hold anyone responsible for the infructuous expenditure of Rs. 93.40 lakh.
Thus, injudicious setting up of the CSC without carrying out
any cost benefit analysis resulted in an infructuous expenditure of Rs. 93.40
lakh.
Western Coalfields Limited
4.7.1 Avoidable loss of Rs. 105.50 crore
Due to non-recovery of electricity charges from the
employees, the Company suffered a loss of Rs. 105.50 crore.
The wage structure and terms and conditions of service
including fringe benefits of the employees in the Coal Industry are regulated by
the recommendations of the Central Wage Board for Coal Mining Industry as
accepted by the Government of India. National Coal Wage Agreement - V (NCWA-V)
accepted by the Government of India, inter alia provided that in the
coalfieds areas, where the employees were provided with residential quarters by
the Management and also electricity from the bulk supply obtained from the
Electricity Boards, they would be entitled to a free consumption of 30 units per
residential quarter per month on a uniform basis. It further provided that for
consumption beyond this, they would be required to pay at the same rates at
which the electricity supply undertakings charged the Coal Companies. The
agreement was effective from November 1994.
Audit scrutiny in case of Western Coalfieds Limited (Company)
revealed that the consumption of electricity by the employees was in excess of
the limit and no recovery was made from the employees in contravention of the
terms and conditions of the NCWA-V. During the period from April 1999 to March
2001, for which complete records were made available, the electricity consumed
in excess of above limit worked out to Rs.105.50 crore.
The Management stated (May 2000) that electricity charges
were not being recovered from the employees due to non-installation of meters in
their residential quarters. They further stated (December 2000) that if recovery
of electricity charges beyond 30 units were enforced without the consensus of
the local trade unions, it would result in strike and unrest, causing huge loss
to the Company on account of loss of production etc.
The reply is not tenable since installation of meters was not
an insurmountable problem. In fact, non-installation of meters would encourage
the employees to resort to injudicious use of electricity for their energy
needs. Further, recovery of electricity charges beyond the permissible limit was
to be effected in accordance with the NCWA-V, which has the approval of the
trade unions.
Thus, due to non-recovery of electricity charges from the
employees, the Company suffered a loss of Rs. 105.50 crore over the period of
two years.
The matter was referred to the Ministry in January 2001;
their reply was awaited (October 2001).
|