APPENDIX - XXIII

(Referred to in paragraph 12.10.2.1 at page 66)

Delay in handing over of staff quarters

(Rs in lakh)

Sl
No.

Name of the circle

No. of
cases

Delay in
months

Reason

Financial Implications

1

Andhra Pradesh

111

2-32

Non availability of electrical and municipal water supply drainage problem

68.08

2

Bihar

8

25

Electrical connections not provided

1.94

3

Chennai

3

18-25

Non-completion of electrical work

82.71

4

Gujarat

17

1-14

Slow progress delay in taking over by GMTD, slow progress of work original work rescinded

6.39

5

Karnataka

14

4-9

Telecom. authorities not taken over

4.21

6

Orissa

16

1-24

Delay in fixing of taking over, non-availability of electrical services

4.94

7

Rajasthan

54

2-12

Non-completion of electrical work

2.27

8

Tamil Nadu

40

9-50

Non-completion of electrical work

11.85

9

Uttar Pradesh (West)

27

1-28

Not Available

8.43

10

West Bengal

5

6

Admn. Reasons

1.51

 

Total

295

1 - 50

 

192.33