Sl
No. |
Name of the circle |
No. of
cases |
Delay in
months |
Reason |
Financial Implications |
1 |
Andhra Pradesh |
111 |
2-32 |
Non availability of electrical and municipal water supply drainage
problem |
68.08 |
2 |
Bihar |
8 |
25 |
Electrical connections not provided |
1.94 |
3 |
Chennai |
3 |
18-25 |
Non-completion of electrical work |
82.71 |
4 |
Gujarat |
17 |
1-14 |
Slow progress delay in taking over by GMTD, slow progress of work
original work rescinded |
6.39 |
5 |
Karnataka |
14 |
4-9 |
Telecom. authorities not taken over |
4.21 |
6 |
Orissa |
16 |
1-24 |
Delay in fixing of taking over, non-availability of electrical services |
4.94 |
7 |
Rajasthan |
54 |
2-12 |
Non-completion of electrical work |
2.27 |
8 |
Tamil Nadu |
40 |
9-50 |
Non-completion of electrical work |
11.85 |
9 |
Uttar Pradesh (West) |
27 |
1-28 |
Not Available |
8.43 |
10 |
West Bengal |
5 |
6 |
Admn. Reasons |
1.51 |
|
Total |
295 |
1 - 50 |
|
192.33 |