CHAPTER 11
MINISTRY OF ENVIRONMENT AND FORESTS
11.1 Unfruitful expenditure on construction of staff
quarters
Due to inaccurate assessment of requirement of quarters,
72 of 80 staff quarters constructed at Arid Forest Research Institute remained
vacant since its construction in 1997. As a result, Rs 3.33 crore incurred on
its construction remained unproductive.
Indian Council of Forestry Research and Education (ICFRE),
Dehradun accorded administrative approval and expenditure sanction in December
1993 for the construction of 40 staff quarters at the cost of Rs 176.67 lakh and
in December 1994 for the construction of 40 more quarters at the cost of Rs
120.50 lakh at Arid Forest Research Institute (AFRI), Jodhpur under World Bank
Project.
AFRI, Jodhpur decided to construct 80 quarters at new Campus,
where it already had 99 staff quarters at its main campus, of which 24 were not
occupied. The construction of the 80 quarters was completed in 1997 at the cost
of Rs 3.33 crore. Of these 80 quarters, 72 quarters were not occupied till
August 2001.
The Board of Governors of ICFRE in June 2001, approved a
proposal to rent out surplus residential accommodation at new Campus of AFRI to
other Central Government Departments/Organisations for their employees on
suitable terms and conditions. The Director of AFRI was to finalise the terms
and conditions after consultation with legal advisors. The terms and conditions
were not finalized till August 2001 and a total of 96 quarters were still lying
unoccupied.
The ICFRE, Dehradun stated in September 2001 that the
Institute was in its initial stage and that the 80 additional quarters were
constructed to accommodate all the staff members who were likely to be allotted
in the near future. The contention of ICFRE was not acceptable as against the
total sanctioned strength, only 113 posts were filled up by August 2001. The
remaining 66 vacant posts were mainly in group ‘C’ and ‘D’ categories,
which cannot be filled due to ban on recruitment etc. Ministry of Environment
and Forests endorsed the reply of the ICFRE (November 2001).
In summary, due to deficient planning and inaccurate
assessment, 80 staff quarters were constructed without any need, with the result
an expenditure of Rs 3.33 crore incurred on these 80 quarters remained
unproductive.
|