CHAPTER 6
DEPARTMENT OF SCIENCE AND TECHNOLOGY
6.1 Avoidable expenditure
Failure to take timely action for completion of
construction work resulted in avoidable expenditure of Rs 42.98 lakh on the
power not actually consumed from July 1995 to August 2000.
Satyendra Nath Bose National Centre for Basic Sciences (SNBNCBS),
Kolkata an autonomous body of Department of Science and Technology (DST) planned
to construct its own building at Calcutta in two phases. Phase-I commenced in
December 1990. SNBNCBS, without ensuring funds for construction of Phase-II
entered into an agreement with the West Bengal State Electricity Board (WBSEB),
Kolkata in July 1994 for supply of electricity for a period of five years
ranging from 350 KVA to 1000 KVA for both phases of the proposed building.
As per the agreement, the Centre was required to pay minimum
charges per annum for the contracted demand. SNBNCBS, even before approaching
DST for sanction of funds for Phase-II obtained electric connection from WBSEB
in June 1995. Phase-I of the construction was completed in July/August 1995 and
SNBNCBS shifted to the new campus in January 1996. Phase-II of the construction
was yet to commence as no proposal for expenditure sanction had been sent to
DST. Despite the uncertainty of time schedule regarding Phase-II construction,
the Centre did not approach WBSEB under the provisions of the agreement to
reduce the contracted demand. During the period up to August 2000 the actual
consumption ranged between 210 KVA and 282 KVA. The Centre paid Rs 42.98 lakh as
charges for the shortfall of average minimum guaranteed revenue during this
period in addition to regular charges for electricity consumed.
SNBNCBS approached WBSEB only in May 2000 to reduce the
contracted demand only after expiry of agreement of July 1994 though pointed out
as early as 1996 by Audit. Accordingly, WBSEB reduced the contracted demand
through a fresh agreement on 31 August 2000. Thus SNBNCBS had incurred an
avoidable expenditure of Rs 42.98 lakh for the power not consumed by it during
the period July 1995 to August 2000 as the actual consumption of power was much
below the contracted demand.
SNBNCBS stated in August 2000 that the Centre could not
review the future power demand, as the construction work was uncertain due to
legal case. The reply is not tenable, as the Centre had failed to take
appropriate action to get the contracted demand reduced in view of the
uncertainty of construction under Phase-II. DST has not sanctioned funds for
Phase-II of the construction till October 2001.
Thus, failure to take appropriate action of getting
contracted demand reduced and delay in obtaining sanction of DST for Phase-II of
the construction resulted in an avoidable expenditure of Rs 42.98 lakh on the
power not actually consumed.
Audit reported the matter to the Department in October 2001
who have not replied as of December 2001.
6.2 Avoidable expenditure on water charges
Failure to take timely action to rectify the faulty water
meters led to avoidable expenditure of Rs 11.90 lakh on water charges.
India Meteorological Department (IMD), Pune draws water from
Pune Municipal Corporation (PMC) for IMD campus and Meteorological Observatory
at Agriculture College campus, Pune. The conditions of water supply stipulated
that PMC would charge for the water consumed by IMD on the basis of quota fixed
for each connection or on average consumption whichever was more for the period
the water meters were faulty. Two water meters installed at IMD campus and
Agriculture College campus were faulty. PMC raised bills for water supplied
during the period April 1994 to February 1999 based on bi-monthly quota of 3900
and 240 kilo litres and IMD paid Rs 12.67 lakh in settlement of the claim,
whereas, monthly average consumption was only 60 and 65 kilo litres.
Resultantly, IMD incurred an avoidable expenditure of Rs 11.90 lakh on water
charges during the above period. Even prior to April 1994, IMD paid water
charges based on quota fixed, as the water meters were faulty. The Department
had not provided audit with information required to work out the avoidable
expenditure prior to April 1994.
IMD did not take any effective action to repair/replace the
faulty meters till it was pointed out by Audit in May 1998/February 1999. IMD
got these faulty meters made functional in February 1999/August 1999. PMC
corrected the bills for water consumption during the period March 1999 to
February 2000 on actual consumption. However, PMC refused to admit the claim of
Rs 11.90 lakh from IMD on the ground that it had raised the bills for the water
charges as per the conditions of water supply, hence IMD had not made any excess
payment to it.
Thus, failure of IMD in taking timely action to rectify the
faulty water meters led to avoidable expenditure of Rs 11.90 lakh on water
charges.
Audit reported the matter to the Department in September
2001, who have not replied as of December 2001.
|