Annexure-XV

(Referred to in para 6.1.8.1)

Statement of package-wise delay analysis

 

Sl. No

Name of package

Agency

Contractual Completion date

Actual date of Completion

Delay (month)

 

GLOBAL

       

1.

Continuous Casting Department (G-01)

VAI
L&T
ABB

March,97

Mar,98

12

2.

Installation of Reheating furnace
No.4 and Conversion of RHF 3and2 (GO2)

MECON
Italimpianti

RHF -4-
Oct,95
RHF - 3
Oct,96
RHF - 2
Sept,97

Nov,96
Jan,00
-

13
39.
-.

3.

a) Modernisation of Hot Strip Mill
(HSM)
b) Installation of Coiler-4
c) Conversion of Coiler-3
                        Coiler-2
  (GO3and4)      Coiler-1

SMS (AG)
SMS(I)
SIMPLEX
TGS
ABB
VAI
GFA

Nov, 96

June,96
Nov,96
Feb,97
May,97

Jul,98

Sep,97
Jun,98
Feb,99
Jan,00

20

15
19
24
32

 

INDIGENOUS

       

4.

Slab Transfer Car and BOI wagons (E-01)

NIRMAL and OTHER

June,96

June.98

24

5.

Dumpers (E-02)

Askok Leyland

Sept,95

Dec.95

3

6.

Trucks (E-03)

Telco

Dec,95

Feb.97

14

7.

Truck & Semi Trailor (E-04)

Ashok Leyland

May,96

Aug.96

3

8.

Dumper Placer (E-05)

Hydromech

Oct,96

Feb.97

4

9.

Fire Extinguisher (E-06)

Steelage

Jan,97

Aug.97

7

10.

Fork Lifts (E-07)

Godrej

Aug,97

Apr.98

8

11.

Addl. Equipment and Modi. of Existing eqpt. (IE-01)

HEC

March,96

Oct.98

31

12.

30T Crane with Magnet (IE-02)

HEC

July,96

Mar,99

32

13.

Trolley Line. illumination (IE-03)

MJ Engg.

March,96

Aug,97

17

14.

Lab. Facilities (IE-04)

TTG Indias

Aug,96

Feb.98

18

15.

Inter Plant Services (IE-05)

HSCL

Aug,96

Sep.97

13

16.

Power Supply Facilities (IE-06)

ABB

Sept,96

Mar,99

30

17.

Territory Lighting (IE-07/1)

General Electricals Apar

Sept,96

Feb.99

29

18.

Building illumination (IE-07/2)

Bajaj Elect. .

Aug,96

Nov.97

15

19.

Chilled Water Plant IE (08/02)

NICCO

Aug,96

Aug.97

12

20.

Compressed Air Station (IE-09/01)

Kirloskar

July,96

Mar.99

32

21.

Oxygen Compressor Plant (IE-9/02)

Sulzer

Oct,96

Aug.97

10

22.

Gas Mixing and Boosting Station(IE-10)

NICCO

Sept,96

Sep,99

36

23.

Telecom Facilities (IE-11)

Philips

August 96

Mar.98

19

24.

Scada System (IE-12)

 

Aug,96

Apr,98

20

25.

Railway Signalling (IE-13)

Railway Products (P) Ltd.

Oct,96

Feb,99

28

26.

EOT Cranes and Hoists (IE-14)

Braithwaite

Oct,96

June.98

20

27.

Slag forming Mixer and Graphite Storage Fac. (T-01)

Geetanjali

Oct,96

Nov.97

13

28.

Cooling Tower (T-02)

Paharpur Cooling Tower

Aug,96

Sep.97

13

29.

Acetyline Plant (T-03)

British Oxygen Company

Sept,96

Jan.98

16

30.

Ladle Driers, and Coolers (T-04)

Wellmen

Sept,96

Mar.99

30

31.

132 KV SWITCH YARD (T-05)

Siemens

May,96

Sept.97

16

32.

Water Supply Facilities (T-06)

Bakhtawar Singh Balkishan

Aug,96

Sep.97

13

33.

Civil work for G-01 (C-01)

HSCL

Dec,96

Jun.97

6

34.

Civil work for Scrap yard (C-01/01)

HSCL

June,95

Apr.95

0

35.

Civil work for indigenous packages (C-01/02)

HSCL

June,96

June97

12

36.

Building Structures for G-01 (S-01)

HSCL

Sept,96

Sep.97

12

37.

Structural work for scrap yard Ext. (S-01/01)

HSCl

May,95

Jul.95

2

38.

Structural work for indigenous packages (S-01/02)

HSCL

Dec,96

Nov.97

11