Audit Reports
Railways
Report No.22 of 2017 - Performance audit Union Government Electrification Projects Reports of Indian Railways
Overview
Audit reviewed the various stages of electrification projects management including approval process, identification of implementing agency, project planning, project execution by various implementing agencies and post project utilisation of the completed RE Projects.
It was noticed that the pace of electrification in terms of RKMs improved. However, audit noticed delays in every stage of project planning to project execution in RE projects reviewed, which indicated that there is scope to further improve the pace of electrification. It led to increase in the capital cost of the projects and in the loss of opportunity of cost of money of the capital invested.Delay in completion of projects also led to substantial time and cost overrun and non-achievement of projected savings.
Download Audit Report
-
Index of Report No.22 of 2017 - Performance audit Union Government Electrification Projects Reports of Indian Railways
-
Preface of Report No.22 of 2017 - Performance audit Union Government Electrification Projects Reports of Indian Railways
-
Executive Summary of Report No.22 of 2017 - Performance audit Union Government Electrification Projects Reports
-
Chapter 1 - Introduction of Report No.22 of 2017 - Performance audit Union Government Electrification Projects Reports
-
Chapter 2 - Progress of Electrification in Indian Railways of Report No.22 of 2017 - Performance audit Union Government
-
Chapter 3 - Planning of Railway Electrification Projects of Report No.22 of 2017 - Performance audit Union Government
-
Chapter 4 - Execution and monitoring of Railway Electrification Projects of Report No.22 of 2017 - Performance audit
-
Chapter 5 - Post project utilisation of Railway Electrification Projects of Report No.22 of 2017 - Performance audit
-
Chapter 6 - Conclusion and Recommendations of Report No.22 of 2017 - Performance audit Union Government Electrification Projects
-
Appendix of Report No.22 of 2017 - Performance audit Union Government Electrification Projects Reports of Indian Railways
-
Annexure of Report No.22 of 2017 - Performance audit Union Government Electrification Projects Reports of Indian Railways